Dear Expert ,
Our organization is a nature of process industry and production plan are changing frequently , as result every time we need modify PIR and then we have perform MRP RUN through t-code MD02 . This is very tedious to end user .
Hence we want to develop a tool , after changes of plan figure , at the end day , from PBIM and PBED combination, MRP RUN will run will perform atomically.
Please help me how to do the configuration .
Regards,
Amit Biswas