Now the produced batch B1 can be consumed in plant A for producing product of single sales order line item or can be used for producing product of multiple sales order.
In current practice at the time of production at plant B total quantity of B1 is assigned to any one of the sales order from the plant A product and after inspection and movement of stock from QI to UR again assigned to different sales order with movement type 413E.
Now the plant A wants that if the batch B1 is to be consumed for production of multiple sales order separately, then at the time of production of B1 proportionate quantity should get tagged to the respective multiple sales order. So that B1 is blocked for consumption against the production order of those sales order only.
Is this possible to create a single production order for multiple sales order, which as per my knowledge is not possible.