Hi Nelson,
Following are steps to create maintenance strategy
- Go to transaction IP11
- Click on the tab “New Entries” .
- Enter Name, Scheduling Indicator ( Time, Time - Key date, Time - Factory calendar), Strategy Unit, Call horizon.
- Double-Click on the Packages tab
- Click on the tab “New Entries”
- Enter details like Maintenance Package Number, Maintenance Cycle ( e.g. 7 Days), Maintenance Cycle Text ( e.g. weekly)
- Click on Save icon.
Now, you need to assign this Maintenance strategy to a task list. during assignment you can define which operation should be executed at which maintenance cycle.
After this, you need to go to IP42. Enter strategy and create a plan.
Coming to your another query about changing planning plant, could you pleas brief more on it.
Regards,
Amol