You can schedule background MRP run through MDBT (program RMMRP000) for your plants. You can also use the scope of planning to plan the all plants MRP sequence.
Through CM40 you can do the mass dispatch of planned order as per the available capacity.
You can schedule the job for Program PPBICO40 for planned order to production order conversion.